[Robert and Beverly] Lewis Integrative Science Building (formerly Integrative Science Complex, Phase 2)  
 
Elevation Study (North), HDR/THA, July 2009  
Current Status  
Design Development
 
Project Timeline  

Groundbreaking Target: Summer 2010
Occupancy Target: 2012

 
Project Summary  

Location:  North side of campus, north of Deschutes and Oregon Hall and east of Streisinger Hall, along Franklin Blvd

Size: 100,000 gsf of new construction

Legislative Authorization: 2007 Oregon State Legislature — SB-5516-B

Expenditure Limitation: $65,000,000 ($30,000,000 general obligation bonds + $35,000,000 gifts and grants)

Architect: HDR / THA

Construction Manager/General Contractor: Lease Crutcher Lewis

Project Planner(s): Fred Tepfer, Campus Planning and Real Estate, (541) 346-5564
Emily Eng, Campus Planning and Real Estate, (541) 346-5606

Project Manager: Denise Stewart, Facilities Services, (541) 346-2280

 
Project Description  
The Robert and Beverly Lewis Integrative Science Building will be a high performance research facility that provides new opportunities for interaction and integration across scientific disciplines. The building will connect to others in the Lokey Science Complex and provide expanded facilities for research focused toward understanding brain function, improving human health, developing safe technology and achieving sustainability. The building will include research laboratories, faculty offices, common areas, shared resources, an imaging center that will house an fMRI, facilities to study effects of gene transplantation on behavior, and a neuroinformatics center for data processing and analysis.
 