Fenton Hall Deferred Maintenance & Renovation  
 
   
Current Status  
 
 
Project Timeline  


 
Project Summary  

Location:  1021 East 13th Avenue

Size:

Legislative Authorization: 2007 Legislature — SB-5516

Expenditure Limitation: $5,591,900

Funding: $2,480,500 G-Bonds; $3,111,000 Energy Loans

Architect: Robertson Sherwood Architects

Construction Manager/General Contractor: TBD

Project Planner: Gene Mowery Planning Associate, 346-5593

Construction Project Manager: George Bleekman, Facilities Services, (541) 346-2625

 
Project Description  
The scope of the current project includes seismic structural upgrades, retrofitting existing heating and ventilation systems with more energy efficient HVAC systems, and installing an elevator to increase accessibility to all floors. The selected firm will provide all necessary professional services for schematic design through construction administration. Although this is a deferred maintenance project, we anticipate significant demolition to accomplish the maintenance upgrades. The University will want to take advantage of opportunities presented by the necessary demolition to improve the operational layout of the spaces. Additionally, replacement of the 1914 stacks addition is under consideration. Should additional funding be obtained to support the replacement of the stacks addition, the resulting contract for this commission will be amended to accommodate the services required to execute that work.
 
Links  

Fenton Hall Study March 2008

 
 
Page Updated:November 11, 2009
 