Baseball Park  
   
   
Current Status  

Baseball Park Conceptual Design Study completed

Phase I - Field Package: Completed.

Phase II - Stadium Design: Construction Documents near completion.

Construction Manager / General Contractor selection completed

 
Project Timeline  

Phase II - Stadium Package: Begin Construction June 2009; Complete Feb 2010.

 
Project Summary  

Site: Northwest corner of the east side of Autzen Stadium

Size: TBD

Legislative Authorization: June 2008 Emergency Board Session

Expenditure Limitation: $20 million gifts

Total Project Budget: $15 to $18 million

Architect- Concept Design Study: Robertson Sherwood Architects, Eugene
                   Phase I, Field Package: Cameron McCarthy Gilbert Scheibe, Landscape Architects, Eugene
                   Phase II, Stadium: DLR Group, Portland

Construction Manager / General Contractor: Lease Crutcher Lewis, Portland

Project Planner: Gene Mowery, Campus Planning and Real Estate, 6-5593

 
Project Description  

Phase I - "Field Package": Phase I includes the baseball field, player development area, scoreboard, video board, fencing, lighting, associated infrastructure, and temporary grandstands, dugouts, press box, toilets, and concessions. This portion of the project will be ready for competitive baseball play by spring 2009.

Phase II - "Stadium Package": Phase II is a stadium designed to accommodate 3,000 to 4,000 fans, that will include a clubhouse, press box, donor suites, concessions, plaza and landscape build-out, and associated infrastructure.  Phase II construction is expected to be complete by spring 2010.

 
Links  

 
 